AI Data Center Power & Capacity Tracker

LIVE REFERENCE  ·  UPDATED MONTHLY

The AI Data Center Power & Capacity Tracker

The numbers that actually determine what you'll pay, how long you'll wait, and where you can build in 2026 — vacancy, grid queues, pricing, and every major power deal, in one place, sourced and updated by TechInfraHub.
1.4%
North American vacancy, H1 2026
4-10 yrs
Grid interconnect wait, primary markets
$64B
Projects blocked/delayed by local opposition
80.4%
Nuclear capacity committed, not yet operational
Last updated: September 2026 — next update due October 2026. Every figure below is sourced; see methodology at the bottom.
Supply & Pricing

Colocation vacancy and per-kW pricing, by market

Power availability, not floor space, is now the constraint everywhere. Vacancy is at record lows and asking rents are moving fastest in the mid-size (3–10 MW) tier.

National vacancy (250–500kW tier)
1.4%
Down from 1.6% a year earlier. Northern Virginia: 0.2%.
National avg. asking rent
$196/kW-mo
Up 6.6% YoY, 250–500kW requirement band.
Mid-size tier (3–10MW) rate growth
+8.3%
Fastest-repricing segment, H1 2026.

MarketAsking rent ($/kW-month)YoY changeGrid interconnect wait
Northern Virginia$190–$235+1.5% (10MW+ tier)4+ years
Chicago$200–$230+14.7%Moderate
Phoenix$170–$210~flat8–14 months
Silicon Valley / HillsboroHighest in US+19% (10MW+ tier)Severely constrained
New York Tri-State+19% (10MW+ tier)Long
London~8 years
Amsterdam~10 years
Power Supply

Every major hyperscaler nuclear & power deal

9.8 GW committed across 13 deals. Only 1.92 GW is actually operational — the rest is a bet on the 2030s, not a fix for the power crunch today.

CompanyCapacitySourceStatus
Amazon1.92 GWTalen Energy / Susquehanna plantLive — since Jun 2025
Microsoft835 MWConstellation / Three Mile Island restartTargeted H2 2027
AmazonUp to 960 MWX-energy Xe-100 SMRs2030s, not started
Google500 MWKairos Power SMR fleetFirst reactor ~2030
MetaUp to 6.6 GWTerraPower, Oklo, Vistra, Constellation2032–2035

Reading this table: only deals tied to an existing, already-built plant (Amazon/Talen, Microsoft/TMI) are delivering real power. Every new small modular reactor deal is a decade-plus bet — full breakdown in Big Tech's Nuclear Power Bet →
Site Risk

Regulatory & community opposition

Local opposition is now blocking or delaying more capacity than power or fiber constraints alone.

Blocked
$18B
Delayed
$46B
Activist groups, 24 states
142
States weighing bans
14+
Cooling

Liquid cooling adoption

The efficiency case is overwhelming; adoption is still catching up.

Deployed today
19%
Planning 12–24mo
36%
Market CAGR to 2033
28.7%
AI-optimized build cost
$15-20M/MW

Turn these numbers into your own decision

The tracker tells you what the market is doing. The Data Center Buyer's Toolkit turns it into your actual cost, your vendor comparison, and your negotiating position.

Methodology & sources: figures are compiled from CBRE North America Data Center Trends H1 2026, Inflect's 2026 Colocation Trends report, ColocationScout's 2026 Pricing Benchmarks, Data Center Watch's project opposition tracker, Data Center Frontier, Axis Intelligence's Nuclear Readiness Gap Index, SMR Intel's deal tracker, and the GlobeNewswire/mgrid.org liquid cooling market reports. Full citations are linked within each corresponding article above. This page is refreshed monthly as new data is published; figures reflect the most recent published data at time of update, not real-time feeds.